 * Get all subopi units on-net. 
 * Inventory garage tool rack 
 * Inventory/organize/make complete sets of and inventory/document garage drill/driver/specality bits  
 * Inventory art room 
 Remaining items to complete.  

 * Plug in last two server power cables  
 * Plug in 3rd hard drive to ultix 
 * Resolve issues with second hard drive not showing up in ultix 
 * Deploy environmental and security sensors in server room (in progress) 
 * Finish deploying (zwave/zigbee/proprietary) sensors (temp / humidity / door / window / alarm keypads)    in server room / elsewhere  
 * Ensure all Ecobee sensors are (optimally) deployed 
 * Badge control server room door 