Support #290

closed

Deploy subo dev rack

Added by Charles N 17 days ago. Updated about 12 hours ago.

Status:
Closed
Priority:
Normal
Assignee:
Target version:
-
Start date:
05/07/2025
Due date:
05/10/2025
% Done:

100%

Estimated time:

Description

  • Install power strip/top of rack switch (done)

  • Connect power strip to power and top of rack switch to network (done)

  • Install DUT power strips (done)

  • Install distribution access points (done)

  • Install first shelf (done)

  • Install second shelf (obtain more rack screws from Altex)

  • Flash, power/ethernet connect ground station units (and supporting systems)

  • Flash, power/ethernet connect payload units (and supporting systems)

Actions #4

Updated by Charles N 17 days ago

  • Status changed from New to In Progress
Actions #5

Updated by Charles N 17 days ago

  • Due date set to 05/10/2025
  • Target version set to 10
Actions #6

Updated by Charles N 10 days ago

  • % Done changed from 40 to 60
Actions #7

Updated by Charles N 8 days ago

  • % Done changed from 60 to 100
Actions #8

Updated by Charles N 8 days ago

  • Status changed from In Progress to Closed
Actions #10

Updated by Charles N 8 days ago

  • Target version changed from 10 to 12
Actions #11

Updated by Charles N about 12 hours ago

  • Target version deleted (12)